Cryostat Installation Begins for $3.3bn DUNE Neutrino Experiment

Engineers have begun installing cryostat infrastructure for the $3.3bn DUNE-LBNF neutrino experiment, 1.6 km underground in South Dakota, with CERN leading the build.

By Rebecca Stone3 min read579 words

Summary

  • Cryostat installation has begun for the $3.3bn DUNE-LBNF experiment 1.6 km underground in South Dakota.
  • Four detector tanks will each hold 17,000 tonnes of liquid argon cooled to 88 K.
  • Some 6200 tonnes of supporting steel began being lowered underground in May.
  • CERN leads cryostat design and installation — its first major contribution to an experiment outside Europe.
  • Detector completion is planned for 2030, with neutrino measurements from Fermilab's 1300 km-distant beam starting in 2031.
US underground neutrino experiment begins cryostat installation
FigureUS underground neutrino experiment begins cryostat installation — Kost9n4 / pixabay

Engineers have started installing the infrastructure that will house the giant cryostats of the $3.3bn Deep Underground Neutrino Experiment–Long-Baseline Neutrino Facility (DUNE-LBNF), marking the transition from planning to construction for one of the largest particle-physics projects on US soil.

The work is taking place 1.6 km underground at the Sanford Underground Research Facility in South Dakota. Two caverns, each roughly 150 m long and seven storeys tall, will hold DUNE's four neutrino detector tanks. Each tank will contain 17,000 tonnes of liquid argon cooled to 88 K (minus 185 °C, the temperature at which argon stays liquid at atmospheric pressure).

The scale of the mechanical engineering is itself a specification worth noting. The cryostat modules will be held in place by some 6200 tonnes of steel, and lowering that steel underground began in May. That mass of support structure approaches the steel content of a mid-sized suspension bridge, a measure of what it takes to stabilise cryogenic vessels of this volume in rock.

Who is building it, and why that matters

CERN, the particle-physics laboratory near Geneva, is leading the design, construction planning and installation of the cryostats. According to the project's own account, this is the first time CERN has made contributions of this significance to an experiment located outside Europe. For R&D managers tracking international consortium structures, the arrangement places a European laboratory in a lead engineering role on a US-hosted, Department-of-Energy-anchored programme.

CERN director general Mark Thomson framed the milestone in institutional terms. "Collaboration is in CERN's DNA, and our contribution to DUNE is a brilliant example of cross-organizational partnership," he said. "After years of planning and careful coordination, I am thrilled to see that we are ready to start installation."

What the detectors will actually measure

The detector apparatus is planned for completion by 2030. Beginning in 2031, DUNE will measure neutrinos generated by Fermilab's accelerator complex, located roughly 1300 km away just outside Chicago. That distance — the "long baseline" in the facility's name — lets neutrinos (nearly massless neutral particles that rarely interact with matter) oscillate between their three types over a meaningful flight path before detection.

Once fully operational, DUNE-LBNF aims to study the properties of neutrinos in unprecedented detail, together with the differences in behaviour between neutrinos and antineutrinos (the antimatter counterparts of neutrinos). Those comparisons bear directly on the question of why the universe contains matter but almost no antimatter.

Fermilab director Norbert Holtkamp set the project's standing within the laboratory's portfolio plainly. "DUNE is Fermilab's top priority," he said. "Once underway, DUNE has the potential to help us broaden our fundamental understanding of our universe, as well as potentially open the door to new technological advances."

What remains untested

The commissioning schedule leaves a long validation window. Installation has begun, but detector completion is a 2030 target and first physics measurements are not expected before 2031 — a five-plus-year horizon over which cryogenic performance, argon purity at the 17,000-tonne scale, and beam delivery from Fermilab must each be demonstrated. The statements from both laboratory directors describe potential rather than measured results.

With steel already descending the shaft and cryostat infrastructure now going in, the project's next verifiable milestones will be the completion of the first cryostat module and the start of argon filling — steps that will show whether the 2030 completion date holds.

via lbnf-dune.fnal.gov (Original)

Filed under

  • dune
  • neutrino-physics
  • cryogenics
  • cern
  • fermilab
Share this article:

More from Rebecca Stone

Rebecca Stone

Show full bio

Market editor covering regulation, policy and their impact on research and development at Hypothesis Wire.

274 articles

References

  1. Fermilab's 34,000-Ton Liquid Argon Plan Runs Through a Six-Inch Pipe
  2. INFN Legnaro opens new chapter on heavy-element origins
  3. Sandia tops out $400M power sources facility, targets 2028 completion
  4. Geothermal R&D Act Targets Superhot Rock to Cut Costs
  5. ORNL opens Translational Research Capability, its newest facility

« Previous articleNext article »